The Wells Area Improvement Project is underway. The Project has two major elements:
CSX Transportation contractor RJ Corman has completed the first Project element, the 6-mile extension of the 2-mile passing track in Wells. The additional track capacity will improve train reliability and increase schedule flexibility for both Downeaster and freight trains.
The second Project element, construction of a new platform at Wells Transportation Center, began March 3, 2025. One boarding platform currently exists adjacent to the Wells station building. That platform will be rebuilt, and a second platform will be constructed across the tracks. The platforms will be connected via an overhead pedestrian bridge. The second platform will allow Downeaster trains operating in opposing directions to board and alight Wells passengers at the same time. Great Falls Construction, based in Gorham, Maine, has been awarded the construction contract.
Downeaster trains will remain in operation throughout the Project, but passengers will notice differences at the Wells Station. There will be temporary modifications to vehicular circulation around the station to accommodate construction staging areas and access roads. A temporary Downeaster boarding platform will be built adjacent to the station building to separate passengers from construction activities.
The new expanded facility is expected to be completed late in the fall of 2026. The Project improvements will allow for additional Downeaster train service between Brunswick and Wells aimed to provide commuters with car-free access to and within the greater Portland Region during rush hour.
Project Milestones
Date
Goal
March 2025
Construction of the new platform and pedestrian bridge begins
February 2025
Contract for construction of the new platform and pedestrian bridge awarded to Great Falls Construction of Gorham, Maine
December 2024
CSX contractor, RJ Corman completes the 6-mile extension of the siding track
Project Budget
The total project budget is $31,095,403.
Seventy-three percent of the total is being paid for through the Consolidated Rail Infrastructure and Safety Improvement Grant awarded to NNEPRA by the Federal Railroad Administration in 2019 matched by a 20 percent contribution from the Maine Department of Transportation and six and a half percent contribution from CSX .
Project Photos
March 2025- Downed trees mark the site where the new second passenger platform will be built.March 2025- Tree clearing underway.March 2025- Construction of the temporary access road begins.March 2025- Great Falls Construction and R.J. Grondin & Sons mobilize at Wells StationDecember 2024- doubletrack extension is completeDecember 2024- The newly extended track in use by the Amtrak DowneasterSeptember 2024- RJ Corman removes #15 frog panelSeptember 2024- RJ Corman removes #15 frog panelSeptember 2024- RJ Corman removes the turnout panel (switch) at CPF 228.August 2024- CSX welding contractor.August 2024- RJ Corman installs the second turnout.July 2024- RJ Corman spreads stone ballast throughout the new panel.July 2024- RJ Corman installs the pre-built #20 turnout panel.July 2024- To date, RJ Corman has constructed 6,000 track feet (TF) of skeletonized trackJuly 2024- RJ Corman has approximately 3,000 TF single plated of ties laid out.May 2024- RJ Corman’s crew lays out ties.May 2024- Track construction is underway on Wells Siding.May 2024- Track construction is underway on Wells Siding.January 2023- The CSX Rail Train carrying 115lb continuously welded rail.January 2023- Crews offloading the rail in Wells. January 2023- The CSX Rail Train arrives at CPF 228 carrying 115lb continuously welded rail that will extend the existing siding six miles between Wells, ME and North Berwick, ME.September 2022- Final culvert. September 2022- Construction of culvert wingwall. August 2022- Precast concrete culvert being set and connected. August 2022- Precast concrete culvert being set. August 2022- CPM Construction crews continues work on the Wells culvert repair. July 2022- Crews driving sheet piles into the ground using a vibrating hammer. July 2022- HP Fleming driving sheet piles for the culvert rehabilitation east of Varney’s crossing in Berwick, ME. April 2022- Pan Am signal department covering conduit for new interlocking. April 2022- Pan Am signal department installing electrical conduit. April 2022- Shaw Brothers Construction cutting sub grade. March 2022- Shaw Brothers Construction cutting sub grade for the new siding track before placing ballast. March 2022- Shaw Brothers Construction and Beaulieu Logging chipping trees along the railroad right-of-way. March 2022- Tree clearing, Berwick Maine February 2022- Project survey team